Nordic EPOD, the data-centre power-module joint venture between the Norwegian-rooted CTS Group and the power-management company Eaton, formally inaugurated its factory in Viana do Castelo on Thursday, 19 November, and at the same ceremony laid the first stone of a second factory on the same campus. The company now says the site will employ 2,000 people once both plants are running. The first factory already has 250 workers, according to the Viana do Castelo municipality.

NorthSouth HQ has followed the project since it was announced. We reported the start of production in September, when the reported headcount was about 120, and the first unit shipped for export on 21 October. Until last week the stated ceiling was about 500 jobs. The 2,000 figure is a new and much larger target, and it depends on a plant that has not yet been built.

What was announced

The municipality’s statement says the campus, between the parishes of Darque and Vila Nova de Anha on the south bank of the Lima, covers 110,000 square metres. The first factory has 21,000 square metres of floor area; the second will have 17,000 square metres. Together, the municipality says, the two plants will produce 900 EPODs a year, double the roughly 450 a year planned for the first factory. O MINHO’s report gives the first factory’s area as 20,000 square metres.

On timing, O MINHO quotes Francisco Reis, whom it describes as the group’s director in Portugal and whom the municipality calls CEO of CTS Portugal: “We expect to finish the factory at the end of next year. I would say that, certainly, by the end of 2027 and the start of 2028 we will be producing” (NorthSouth HQ translation). Reis declined to give the cost of the new plant. The first factory was a €50 million investment by CTS Group and Eaton, according to both the municipality and O MINHO.

O MINHO also reports that, with the second plant complete, the group expects turnover of €1.8 billion to €2 billion. That compares with the €650 million a year previously given for the first factory at full output. These are company targets, not results.

“Production for 2027 is already full”

Reis gave demand as the reason for the expansion. “We already have all our EPOD production complete for 2027,” he told O MINHO. The municipality repeats the earlier line that orders are secured until June 2027, that about 90% of output is for export, and that the first markets are Europe and the Middle East. The first factory began with two shifts and will extend operations next year.

At the ceremony Reis called the plant “the largest EPOD factory in Europe” and said CTS “will be one of the largest employers in the Alto Minho region” and the largest factory in Viana do Castelo by turnover. “When the campus is complete, it will have 2,000 people,” he said, as quoted by the municipality. CTS Group chief executive Filip Schelfhout repeated the figure: “here, in Viana do Castelo, we will employ 2,000 people.” Reis explained the choice of site by its location 900 metres from the city’s commercial port, close to the A28 motorway and within reach of Porto airport.

Mayor Luís Nobre called it “the most transformative project that has ever happened in industrial terms in Viana do Castelo”. According to O MINHO, he said the municipality’s exports stood at about €1 billion when the installation process began, and that this investment could bring them to €2 billion.

Some figures that do not yet line up

The two main reports differ in places. The municipality says the first factory “expects to create about 500 jobs”; O MINHO says the target for that plant is 700. O MINHO’s opening paragraph says the new factory will make “cooling systems” from late 2027, while the rest of its report, and the municipality’s statement, describe it as an EPOD plant that doubles output to 900 units a year. Neither source breaks the 2,000 jobs down by plant or gives a hiring timetable. Correio do Minho’s report of 21 November repeats the municipality’s figures for the 250 current workers, the €50 million investment and the 2,000 target. Earlier NorthSouth HQ reporting described Viana as the group’s second EPOD site after Hanekleiva in Norway; the “second factory” announced last week is a second plant in Viana itself.

Why it matters for the corridor

Nordic EPOD went from 120 to 250 staff in about three months, which suggests the hiring plan is real. Doubling capacity before the first plant has been open six months is a bet that data-centre demand will hold beyond the order book. For suppliers in the Alto Minho and Porto region (steelwork, cabling, switchgear, transport, and the training providers the plant will need), a 2,000-person campus would be a large local customer, and, if Reis’s claim holds, one of the biggest industrial employers in the Alto Minho. Three things to watch: a disclosed investment figure for the second plant, a clear answer on what it will make, and whether CTS names customers for 2027 and beyond.

Sources: Câmara Municipal de Viana do Castelo, “Nordic EPOD avança com segunda fábrica com ambição de chegar aos 2.000 trabalhadores em Viana do Castelo”, 19 November 2026; O MINHO, “Multinacional avança para a segunda fábrica e vai chegar aos 2.000 trabalhadores em Viana do Castelo”, 19 November 2026; Correio do Minho, “Nordic EPOD com ambição de chegar aos 2.000 trabalhadores”, 21 November 2026; earlier NorthSouth HQ reporting (June, September and October 2026).